Ontario Lifting Suspension Of Lien Periods
Download PDF- Industry Alerts
- Toronto
Click “Subscribe Now” to get attorney insights on the latest developments in a range of services and industries.
On March 20, 2020, the Ontario government introduced an emergency order under the Emergency Management and Civil Protection Act which suspended the running of limitation periods, including those under the Construction Act, by way of Ontario Regulation 73/20 (the “Regulation”). The suspension was retroactive to March 16, 2020.
One of the perhaps unintended consequences of this order was the suspension of the deadline for suppliers of goods and services on construction projects to register / perfect a lien (“Lien Periods”). By suspending the Lien Periods owners could no longer release holdbacks on construction projects without the risk of having a supplier of goods or services lien the subject property after release of the holdback – resulting in adverse consequences to the owner who may have to pay additional amounts for the same supply of goods and or services.
Although lenders who fund draw requests during the suspension of the Lien Periods maintain their priority relative to future liens (assuming the lender conducts a lien search at the time of funding the advance), there could still be adverse consequences to an unwary lender related to potentially inaccurate determination of project lien holdbacks in the calculation of the “costs to date” margin and the extended period during which a lien could be registered against the project lands.
As expected, the Ontario government has addressed these issues by ordering an amendment to the Regulation which amendment lifts the suspension of limitation periods and procedural time periods under the Construction Act.
In a letter dated April 9, 2020, the Attorney General of Ontario stated, “The suspension will be lifted on April 16, 2020, to give the industry time to prepare for these changes. Once lifted, parties will have the same amount of time to meet a deadline that had been remaining before the suspension began on March 16, 2020.”
This is welcome news to lenders, developers, construction trades, and suppliers.
In these circumstances, we recommend that care be taken to ensure that all draw requests properly calculate the project lien holdback amount factoring in (i) the period remaining prior to the beginning of the suspension on March 16, 2020 and (ii) resumption of the running of the limitation period commencing on April 16, 2020.
Please Note: These materials do not constitute legal advice. Government initiatives, announcements and regulations in response to the COVID-19 situation continue to evolve and change frequently. As such, it is important to ensure you are aware of current information and that you consult with a lawyer before making your business decisions. For further information please contact the authors.Related Practices
Recent Insights
- Industry Alerts UPDATE (March 1, 2021) – New COVID-19 Public Health Measures in Effect in Ontario
- Industry Alerts Ontario Government Issues Order to Temporarily Ease Shareholder and Director Meeting Requirements Due to the COVID-19 Pandemic
- Industry Alerts Virtual Witnessing of Wills and POAs During COVID-19
- January 2022 Industry Alerts Dickinson Wright COVID-19 Resource Guide
- December 20, 2021 Industry Alerts Private Employer Vaccine Mandate Moves Forward as Sixth Circuit Dissolves Fifth Circuit’s OSHA ETS Stay
- November 04, 2021 Industry Alerts The Private Employer COVID-19 Vaccine Mandate is Here: What Employers Need to Know
- September 28, 2021 Industry Alerts COVID-19 Surge Medical Leave Refresher for Employers
- September 16, 2021 Industry Alerts Why President Biden’s Plan to Vaccinate the Unvaccinated in Private Employment is a Lot of Buzz, but Likely Little Sting
- May 24, 2021 Industry Alerts HHS Announces the COVID-19 Vaccine Coverage Assistance Fund